CDB Allocates GBP14.4 Million for Montserrat’s Port at Little Bay

Marine access to the island of Montserrat is set to improve, as the Board of Directors of the Caribbean Development Bank (CDB) has approved a grant of GBP14.4 million (mln) or XCD 52.05 million to develop the port at Little Bay.

According to a statement from the CDB, the funds are being provided through the United Kingdom Caribbean Infrastructure Partnership Fund (UKCIF), and will assist in financing the construction of an offshore breakwater and quay.

Head of Infrastructure Partnerships at CDB, Andrew Dupigny, noted that the development of the port is critical to providing a safe harbour and accessibility for vessels up to 150 metres in length.

“The current jetty at Little Bay is exposed to rough seas intermittently, as there is no offshore breakwater. This makes it unsafe for vessels to dock at times, and means that Montserrat is unable to provide a continuous safe harbour for cruise ships, ferries, yachts, cargo and other vessels, which impacts economic activities on the island. The development of the port is seen as vital for Montserrat’s economic recovery and sustainability”, said Dupigny.

Rough seas stopped the Carib Sun from docking in Little Bay. The Star Legend is visible in the back. (Nerissa Golden File Photo)

Currently, rough seas cause significant downtime at the existing port, and 58 out of 475 ships were unable to berth in 2016. Climate change is likely to exasperate the situation, with increased and more frequent storm conditions and sea level rise expected. The construction of an offshore breakwater is therefore particularly important. It will help to create a safe harbour that is climate resilient and adequately protected. Port development will also support the growth of Montserrat’s tourism sector, improving access and connectivity to the island.


In addition, sections of the harbour will be dredged to allow larger vessels to berth along the jetty. This will allow for larger rescue ships to be positioned appropriately, should there be a mass evacuation event caused by the eruption of the Soufriere volcano.

It is expected that phase one development of the port development works will be completed by 2021. Counterpart financing of GBP7 mln will be provided by the Government of Montserrat.

UKCIF provides grant financing to eight Caribbean countries eligible for Overseas Development Assistance, and UK Overseas Territory, Montserrat. The project is consistent with CDB’s strategic objective of supporting inclusive and sustainable growth and development, as well as its corporate priority of strengthening and modernising social and economic infrastructure.